2026 Refinery Turnaround Schedule – Texas City & Galveston Area

Turnaround Schedules

2026 Refinery Turnaround Schedule – Texas City & Galveston Area

Planned and rumored turnaround schedules for major refineries within 30 miles of Hitchcock, TX — updated monthly. Book your RV site early during peak turnaround season.

Why Turnaround Season Fills Our Park Fast

Refinery turnarounds bring thousands of contract workers to the Texas City and Galveston area every year. Lazy D RV Park — just 3–5 miles from the major Texas City plants — is one of the closest full hook-up RV parks to the refinery row. Sites fill up weeks in advance during peak turnaround months. Book early.

Schedule Disclaimer

Turnaround dates are based on publicly available information, industry sources, and historical patterns. Schedules are subject to change without notice. Always confirm directly with your contractor or staffing agency. This page is updated monthly — last updated July 2026.

Disclaimer: Turnaround dates are based on publicly available information and industry sources. Schedules are subject to change. Always confirm with your contractor or staffing agency. Last updated .

Refinery Turnaround Schedules

Marathon Petroleum – Texas City Refinery

Texas City, TXCapacity:76,000 bpd
4 mi from park

Crude Unit / CDU

Planned

Start

September 2026

Duration

6 wks

Workers

800–1,200

FCC / Fluid Catalytic Cracker

Rumored

Start

February 2027

Duration

5 wks

Workers

600–900

Valero – Texas City Refinery

Texas City, TXCapacity:245,000 bpd
5 mi from park

Hydrocracker / HCU

Planned

Start

October 2026

Duration

7 wks

Workers

1,000–1,500

Coker Unit

Rumored

Start

March 2027

Duration

5 wks

Workers

700–1,000

BP / Amoco Chemical – Texas City

Texas City, TXCapacity:Chemical complex
5 mi from park

Aromatics / Benzene Unit

In Progress

Start

August 2026

Duration

4 wks

Workers

400–700

Olefins Unit

Rumored

Start

January 2027

Duration

6 wks

Workers

600–900

INEOS Oligomers – Texas City

Texas City, TXCapacity:Petrochemical
5 mi from park

Polyalphaolefin Unit

Planned

Start

November 2026

Duration

3 wks

Workers

200–400

LyondellBasell – Houston Refinery

Houston, TXCapacity:268,000 bpd
28 mi from park

Crude / Vacuum Unit

Planned

Start

October 2026

Duration

8 wks

Workers

1,200–1,800

Phillips 66 – Sweeny Refinery

Old Ocean, TXCapacity:247,000 bpd
30 mi from park

Reformer / Hydrotreater

Rumored

Start

September 2026

Duration

5 wks

Workers

700–1,000

Book Your Site Before Turnaround Season