2026 Refinery Turnaround Schedule – Texas City & Galveston Area
Planned and rumored turnaround schedules for major refineries within 30 miles of Hitchcock, TX — updated monthly. Book your RV site early during peak turnaround season.
Why Turnaround Season Fills Our Park Fast
Refinery turnarounds bring thousands of contract workers to the Texas City and Galveston area every year. Lazy D RV Park — just 3–5 miles from the major Texas City plants — is one of the closest full hook-up RV parks to the refinery row. Sites fill up weeks in advance during peak turnaround months. Book early.
Schedule Disclaimer
Turnaround dates are based on publicly available information, industry sources, and historical patterns. Schedules are subject to change without notice. Always confirm directly with your contractor or staffing agency. This page is updated monthly — last updated July 2026.
3–5 Miles from Refinery Row
Lazy D RV Park sits at 6202 Delaney Road in Hitchcock, TX — just off I-45, putting you 3–5 miles from the Marathon, Valero, BP, and INEOS plants in Texas City. That's a 10-minute drive with no highway traffic, compared to 30–45 minutes from Houston-area parks.
Built for Working Crews
70 full hook-up sites with 30/50 amp electric, water, and sewer. Gated entry for security. 24-hour laundry. Air-conditioned restrooms and showers. Free Wi-Fi. On-site management. Everything a working crew needs after a long shift.
Monthly Rates That Make Sense
Monthly rates start at $570/month (30 amp) or $590/month (50 amp). Weekly rates at $220/week. Daily at $65/night. For a 6-week turnaround, a weekly rate works out to $1,320 total — far less than a hotel room for the same period.
Disclaimer: Turnaround dates are based on publicly available information and industry sources. Schedules are subject to change. Always confirm with your contractor or staffing agency. Last updated .
Refinery Turnaround Schedules
Marathon Petroleum – Texas City Refinery
Unit
Crude Unit / CDU
Start
September 2026
Duration
6 wks
Workers Est.
800–1,200
Unit
FCC / Fluid Catalytic Cracker
Start
February 2027
Duration
5 wks
Workers Est.
600–900
Valero – Texas City Refinery
Unit
Hydrocracker / HCU
Start
October 2026
Duration
7 wks
Workers Est.
1,000–1,500
Unit
Coker Unit
Start
March 2027
Duration
5 wks
Workers Est.
700–1,000
BP / Amoco Chemical – Texas City
Unit
Aromatics / Benzene Unit
Start
August 2026
Duration
4 wks
Workers Est.
400–700
Unit
Olefins Unit
Start
January 2027
Duration
6 wks
Workers Est.
600–900
INEOS Oligomers – Texas City
Unit
Polyalphaolefin Unit
Start
November 2026
Duration
3 wks
Workers Est.
200–400
LyondellBasell – Houston Refinery
Unit
Crude / Vacuum Unit
Start
October 2026
Duration
8 wks
Workers Est.
1,200–1,800
Phillips 66 – Sweeny Refinery
Unit
Reformer / Hydrotreater
Start
September 2026
Duration
5 wks
Workers Est.
700–1,000
Book Your Site Before Turnaround Season
Monthly rates from $570/month. Weekly rates from $220/week. Call (409) 974-0122 or book online via RoverPass. Sites fill fast — don't wait.
Reserve Your Site Today
Call (409) 974-0122 or (832) 563-1050 to check availability. Monthly stays get priority placement.